9. USM GS 108-260 Residence Halls Sprinkler Systems
Staff Approval #1:
In accordance with Board Policy §904 (A) Board Approval, Board
staff approved
as submitted by Atherton Consulting Engineers,
Inc., design professional. Approval is requested from the Bureau of Building, Grounds,
and Real Property.
Staff Approval #2:
staff
Approval is requested from the
Bureau of Building, Grounds, and Real Property.
Staff Approval Date:
January 14, 2011
Project Initiation Date:
June 18, 2009
Design Professional:
Atherton Consulting Engineers, Inc.
General Contractor:
N/A
Contract Award Date:
Project Budget:
$2,000,000
Funding Source(s):
HB 1722, Laws of 2009 ($2,000,000)
10. USM GS 108-267 College of Business Building (Pre-Design)
Staff Approval:
as submitted by Eley Associates/Studio
South, design professional. Approval is requested from the Bureau of Building, Grounds,
January 12, 2011
March 2, 2005
Eley Associates/Studio South
EXHIBIT 2
February 17, 2011
Page 5 of 6
$547,413 (Pre-Design Budget)
SB 2010, Laws of 2004 ($547,413)
11. USM GS 108-268 Campus Security Lighting and Code Blue Phone Upgrades
In accordance with Board Policy §904 (A) Board Approval, Board staff
approved the
of the above project in the amount of $300,000. All project
initiations with a project budget of $1,000,000 or less and that use state bond funds or
Ayers
funds as a funding source require staff approval. Approval is requested from the
December 16, 2010
$300,000
HB 246, Laws of 2007 IHL Discretionary Funds ($300,000)
12. USM GS 110-089A Research / Facility (Phase II)
in the amount of ($5,355.00) and seventytwo
(72) additional days to the contract of C. Perry Builders.
in the amount of $15,062.13 and forty-three (43)
additional days to the contract of C. Perry Builders.
December 13, 2010
Change Order Justification: Change Order #2
is necessary to adjust for credits to the
project that include eliminating shades on window Type H, deleting stained concrete as
shown on plans, adding smoke detector and programming, conduit, wire, and labor,
changing the specified biological safety cabinet to a 5 cabinet, adding 15 days to the
contract to execute the above items.
is necessary to install gypsum
board, add two 4 PVC conduits with concrete easements, addition of electrical items,
relocation of tempering valve, and adding 23 weather related delay days to the contract.
Total Project Change Orders and Amount:
Three (3) change orders for a total amount
of $14,846.13
February 24, 2005
Allred Architectural Group
C. Perry Builders
January 8, 2009
$9,041,697.88
SB 2010, Laws of 2004 ($1,971,044.88); Mississippi DMR
($1,700,000); NOAA Grant GRO 02733 ($5,370,653)
Page 6 of 6
13. USM GS 114-017 Gulf Park Campus Upgrades
of the above project in the amount of $50,000. All project
$50,000
HB 246, Laws of 2007 IHL Discretionary Funds ($50,000)